Uganda ignores donor concerns on Karuma

(The GoU is apparently claiming this new dam on the Nile could produce
more energy than some donors believe is possible. The new Bujagali Dam
was also "oversold"--as a 250MW project, when in reality it is
expected to produce much less... see for example http://allafrica.com/stories/201111030117.html)
-----------------------------------------------------------

http://www.theeastafrican.co.ke/news/Uganda+ignores+donor+concerns+on+Karuma+/-/2558/1301908/-/item/1/-/157407l/-/index.html

Uganda ignores donor concerns on Karuma


By ESTHER NAKKAZI

Posted Sunday, January 8 2012 at 14:21

East-West rivalry is emerging as a possible factor in the controversy
surrounding the sizing of Uganda�s 660MW Karuma power project, which
Western donors want built at a much lower rating of 450MW.

Speaking off the record about a debate that has seen donors argue that
the power project is oversized relative to the available stream and
the excess capacity is a wastage of scarce resources, Ugandan
officials now suspect Western opposition to the project could be
motivated by the role Chinese finance and civil contractors are likely
to play in the project.

Ignoring donors who argue that the proposed capacity will be available
only partially during the year, Uganda will this month proceed to
receive bids for the power station, which it urgently needs to bridge
a rapidly growing energy gap.

Uganda is apparently sticking to its guns because � in a departure
from previous power projects, where it has had to deal with donors
from project design to financing, � the country will go it alone this
time, building the power station from its own resources and financing
from friendlier partners.

The turnkey project will be funded by the government while Scandinavia
is the preferred technology source.

With only 9 per cent of its population connected to the power grid,
Uganda still has an official supply gap of 130MW. With demand
increasing by 40MW annually and the economy expected to grow at an
average of 5.5 per cent over the next five years, experts say power
supply will still be chasing demand even if the new power station were
to deliver to its design specification.

Consumers now have to endure 12 hours of power rationing at a time as
contracts for thermal generation tail off in anticipation of the 250MW
power station, which is running a year behind schedule.
Now a permanent feature of Uganda�s energy mix, accounting for up to
30 per cent of available energy, thermal electricity has seen the
domestic tariff rise to Ush426 ($0.21).

Given the initial investment cost for new power projects as well as
the proposed removal of a government subsidy that would see the
consumer tariff double, new hydro capacity is not expected to bring
about a reduction of tariffs in the short to mid-term.

Ministry of Energy officials said the controversial 660MW installed
capacity is at optimum usage. However, they conceded that the 700MW
initially proposed was not sustainable in the long run, but insisted
the 400-450MW that the donor community proposed is not supported from
a technical point of view.

Echoing his permanent secretary, who in an earlier interview told this
newspaper that donor concerns were not informed by feasibility
studies, Henry Bidasala, Assistant Commissioner of the Electrical
Power Division in the Ministry of Energy and Mineral Development,
commented: �We had a presentation by the contractor who did the
feasibility study and the energy donor technical team in attendance
asked all the questions they wanted and seemed okay with it.�

Energy Infratech Pvt Ltd of India carried out the feasibility study
and environmental impact assessment in 2010.

Energy Permanent Secretary Fred Kabagambe Kaliisa had earlier argued
that even if 450 or 500MW were the target generation output, it made
sense to factor in redundancy to assure constant supply at those times
when some units have to be shut down for maintenance.

National Planning Authority officials said Uganda needs to increase
its power generation capacity to 3,500 MW by 2015 as the country
experiences a steadily rising population and economic expansion.
According to the Electricity Regulatory Authority, demand has been
growing by nine per cent per annum since 2009. This translates into an
increase of 40MW per annum.

An independent source said whatever decisions the technocrats were
making in respect of Karuma were feasible and the donor community are
only crying foul because of the possible participation of China and
its rising profile in other projects in Africa.

The donors, led by key financier KfW, at one time said they would
engage a new firm to do an independent feasibility study, but have yet
to do so.

The source said without a new feasibility study, the donors are still
referring to the Norwegian consortium Norpak Power Ltd study that had
developed a �conservative design� in the mid-1990s, informed by the
notion that there was low demand for electricity in Uganda.

Keith Muhakanizi, Deputy Secretary to the Treasury, said the projected
cost would be lower than the initial estimates of $2.2 billion because
of a �new approach.�

Initial design proposals suggest a dam with a headrace, tailrace and
an underground facility housing 6 turbines each with nominal rating of
100MW and a spinning reserve of 10 MW.

It will be located about 3km upstream of Karuma Bridge and 80km
downstream of Lake Kyoga on the River Nile.

Construction of the project will be supervised and managed by the
Uganda Electricity Generation Company, the government nominee and
licensee of the project.
________________________________________________

You received this message as a subscriber on the list: africa@list.internationalrivers.org

To be removed from the list, please visit:
http://salsa.democracyinaction.org/o/2486/unsubscribe.jsp

No comments:

Post a Comment